Carbotura · Circular Advantage Program · Stage 1 Proposal Carbotura · Programma Circular Advantage · Proposta Fase 1

Regione Toscana
Circular Advantage Proposal
Regione Toscana
Proposta Circular Advantage

A 30-year Build-Own-Operate Circular Supply Agreement (with perpetual continuation after Year 30) places 1 ACM facility at €100/tonne ($109 USD) — below the region's €130 blended disposal cost — converting 400 TPD of Tuscany feedstock into a structured royalty receipt stream from Month 13. One CSA structure. Zero Region capex. T0: Q2 2027.

Un accordo Build-Own-Operate di 30 anni posiziona 1 impianto ACM a €100/tonnellata ($109 USD) — al di sotto del costo di smaltimento regionale — convertendo 400 TPD di feedstock toscano in un flusso di canone strutturato dal Mese 13. Zero capex dalla Regione. T0: Q2 2027.

Prepared for: Regione Toscana / ATO Toscana Centro · Costa · SudPer: Regione Toscana / ATO Toscana Centro · Costa · Sud
March 2026
T0: Q4 2026 (assumed)T0: Q4 2026 (assunto)
Deployment: 1 site · 400 TPD Phase Initial (standard Carbotura Phase Initial)Dispiegamento: 1 sito · 400 TPD Fase Iniziale (Carbotura Phase Initial standard)
Authority Commitment QualificationQualifica dell'Impegno dell'Autorità

Eight Commitments · One EngagementOtto Impegni · Un Engagement

Five items are required for every engagement and establish the structural commitment between Regione Toscana and Carbotura. Three optional items signal Regional Authority materials offtake under the CMOA.Cinque voci sono obbligatorie per ogni engagement e stabiliscono l'impegno strutturale tra Regione Toscana e Carbotura. Tre voci opzionali segnalano l'offtake di materiali dell'Autorità Regionale nell'ambito del CMOA.

5 REQUIRED · ALL ELECTED5 OBBLIGATORIE · TUTTE ELETTE 3 OPTIONAL · 0 ELECTED3 OPZIONALI · 0 ELETTE
01REQUIRED
Commit feedstockImpegno feedstock
All designated waste streams legally assigned to Carbotura via CSA · disposal liability removed from Region balance sheet.Tutti i flussi di rifiuti designati assegnati legalmente a Carbotura via CSA · passività di smaltimento rimossa dal bilancio della Regione.
Tuscany: Phase Initial 400 TPD / 146,000 TPY (single facility, 1 ATO zone Phase Initial); Phase Expanded multi-ATO. ATO Centro (Alia SpA) · ATO Costa (Retiambiente SpA) · ATO SudToscana: Fase Iniziale 400 TPD / 146.000 TPY (impianto singolo, 1 ATO Fase Iniziale)
02REQUIRED
Commit land + landfill deedImpegno terreno + atto discarica
Manufacturing Site Deed + Remediation Site Deed transferred to Carbotura · registered title · two independent instruments.Atto Notarile del Sito Produttivo + Atto del Sito di Bonifica trasferiti a Carbotura · due strumenti indipendenti.
IT: atto pubblico registered with Agenzia delle Entrate / Conservatoria dei Registri Immobiliari (manufacturing site TBD ATO zone; remediation site — Peccioli, Pisa)IT: atto pubblico presso Agenzia delle Entrate / Conservatoria (sito produttivo TBD zona ATO; sito di bonifica — Peccioli, Pisa)
03REQUIRED
Commit tax abatementsImpegno agevolazioni fiscali
Local strategic investor instrument · qualifying tax relief for agreed period · condition precedent to CSA execution.Strumento dell'investitore strategico locale · agevolazione fiscale qualificante per il periodo concordato · condizione precedente all'esecuzione del CSA.
IT: ZES (Zona Economica Speciale) designation / regional strategic project instrument — Regione Toscana enabling frameworkIT: designazione ZES (Zona Economica Speciale) / strumento di progetto strategico regionale — quadro abilitante Regione Toscana
04REQUIRED
Receive royalty stream on materialsRicezione flusso canone sui materiali
Circular Royalty™ or Circular Royalty™ (Canone Circolare o Canone Regionale sulle Risorse · pagato da Carbotura ALLA Regione · mai combinato con la Tariffa.
Reported as separate transactions per the Separate Transaction Principle (MR §4.8) · IPSAS accounting standard (Italian public-sector)Riportato come transazioni separate · standard contabile IPSAS (settore pubblico italiano)
05OPTIONAL · SUBJECT TO STUDY
Exogenesis™ landfill miningMining discarica Exogenesis™
Exogenesis™ Programme · APS · fully electric fleet · €50/tonne royalty TO the Region · land restored on completion.Programma Exogenesis™ · APS · flotta completamente elettrica · canone €50/tonn ALLA Regione · terreno ripristinato al completamento.
Tuscany: Peccioli (Pisa) — flagship Italian remediation case (largest active landfill in Tuscany, ~65km from ATO Centro boundary); IPSAS 19 post-closure liability extinguishment at CSA executionToscana: Peccioli (Pisa) — caso emblematico di bonifica italiana (discarica attiva più grande della Toscana); estinzione passività IPSAS 19 all'esecuzione del CSA
06OPTIONAL · NOT ELECTED
Commit offtake for Regional reservesImpegno offtake per riserve regionali
Regional Authority preferential election right over RC3–RC5 manufactured output · best efforts · no take-or-pay.Diritto di elezione preferenziale dell'Autorità Regionale sull'output manifatturiero RC3–RC5 · massimo impegno · senza take-or-pay.
RACMO · Regional Authority Critical Materials Offtake (Tuscany regional construct)RACMO · Offtake Materiali Critici Autorità Regionale (costrutto regionale toscano)
07OPTIONAL · NOT ELECTED
Regional Authority preferential pricingPrezzi preferenziali Autorità Regionale
Preferential rate on RACMO-elected RC3–RC5 output · rate set at CSA negotiation · only meaningful if card-06 elected.Tariffa preferenziale sull'output RACMO-eletto · tariffa fissata alla negoziazione CSA · significativa solo se carta-06 eletta.
RACMA · Regional Authority Critical Materials Authority pricingRACMA · Prezzi Autorità Materiali Critici Regionali
08OPTIONAL · NOT ELECTED
Pre-purchase MAMP paymentPagamento MAMP anticipato
The Region prepays Carbotura under advance purchase structure · required CP for RACMA pricing discount · Carbotura does not deploy capital without receipt.La Regione prepaga Carbotura sotto struttura di acquisto anticipato · CP richiesta per lo sconto RACMA · Carbotura non impiega capitale senza ricezione.
RIRC · Regional Industrial Reserve Corp (IT construct) · institutional reference TBD at CSA negotiation · estimated €50–100M upfrontRIRC · Corporazione Riserva Industriale Regionale (costrutto IT) · riferimento istituzionale TBD alla negoziazione CSA
Sections

§0 — What This Means §0 — Cosa Significa

Canone Circolare™
Circular Royalty™ (Manufacturing Beneficiation)Canone Circolare™ (Beneficiazione Manifatturiera)
OUTFLOW ↑USCITA ↑
Beneficiation Fee: €100/tonne (Yr 1)
+2.5%/yr escalator
Phase Initial: ~€14.6M/yr (146,000 tpy)
Manufacturing Beneficiation Fee · standard structure
Tariffa TMC: €100/tonnellata (Anno 1)
+2,5%/anno escalation
Fase Iniziale: ~€14,6M/anno (146.000 tpy)
INFLOW ↓ENTRATA ↓
Circular Royalty™: 120% of corresponding Fee
+1pp/yr escalator (Year 30 = 148%)
Phase Initial: ~€17.5M/yr (Yr 2)
→ ~€23.1M/yr (Yr 30)
From Carbotura product revenues · 13-month lag
Canone Circolare: 120% della Tariffa corrispondente
+1pp/anno (Anno 30 = 148%)
Fase Iniziale: ~€17,5M/anno (Anno 2)
· Regional Authority Swap
Circular Royalty™Canone Regionale sulle Risorse
OUTFLOW ↑USCITA ↑
€0 Beneficiation Fee
Consideration: site deed at signing

atto pubblico via Agenzia delle Entrate at CSA execution
€0 Tariffa TMC
Corrispettivo: atto del sito alla firma
(Scambio Attivo · unica volta, irrevocabile)
INFLOW ↓ENTRATA ↓
Circular Royalty™: €100/tonne
+1%/yr escalation from Year 2
Phase Initial: ~€14.6M/yr (Yr 2) ($15.9M USD)
→ ~€19.3M/yr (Yr 30) ($21.0M USD)
13-month lag · symmetric Take-or-Pay floor
Canone Regionale sulle Risorse: €100/tonnellata
+1%/anno dall'Anno 2
Fase Iniziale: ~€14,6M/anno (Anno 2)
Exogenesis™ Royalty · Universal Bonus (under the CSA or B)Canone Exogenesis™ · Bonus Universale (come componente della CSA)
Peccioli Landfill (Pisa) — Largest in TuscanyDiscarica Peccioli (Pisa) — La Più Grande della Toscana
CONSIDERATION ↑CORRISPETTIVO ↑
Peccioli landfill deeded at signing

~73,000 tpy extractable estimate
Post-closure care, leachate obligations transfer to Carbotura · IPSAS 19 extinguishment
Discarica Peccioli ceduta alla firma
(Scambio Attivo, secondo strumento)
~73.000 tpy stimati estraibili
INFLOW ↓ENTRATA ↓
Exogenesis™ Royalty: €50/tonne extracted
+1%/yr escalation from Year 2
~€3.65M/yr (Yr 6)
Year 5 post-COD · 13-month lag from first extraction
Canone Exogenesis™: €50/tonnellata estratta
+1%/anno dall'Anno 2
~€3,65M/anno (Anno 6)
One Circular Supply Agreement.Un Accordo di Fornitura Circolare. Regione Toscana executes the CSA. The Exogenesis™ Royalty Bonus is a universal stream available as a CSA add-on — activated when Peccioli landfill is deeded at signing. All three streams are reported as separate transactions per the Separate Transaction Principle (MR §4.8). T0: Q2 2027 (EU pipeline canonical default).Il Canone di Remediation (via Exogenesis™) è disponibile come componente aggiuntivo della CSA. Tutti i flussi sono riportati come transazioni separate. T0: Q2 2027.
Executive Summary — The OfferSintesi Esecutiva — L'Offerta
  • What is being offered: A Build-Own-Operate Circular Supply Agreement for three distributed ACM facilities across Tuscany's three ATO zones — each starting at 200 TPD and designed to expand to 1,000 TPD per site (3,000 TPD total). Carbotura finances, builds, owns, and operates all three facilities. The region's obligation is the Beneficiation Fee per tonne delivered.
  • Cosa viene offerto: Un Accordo di Fornitura Circolare Build-Own-Operate per tre impianti ACM distribuiti nelle tre zone ATO toscane — ognuno con partenza a 200 TPD ed espansione fino a 1.000 TPD per sito (3.000 TPD totali). Carbotura finanzia, costruisce, possiede e gestisce tutti e tre gli impianti. L'unico obbligo della regione è la Tariffa TMC per tonnellata consegnata.
  • What the region commits to: A 30-year Circular Supply Agreement authorizing Carbotura's Build-Own-Operate deployment on three industrial sites (one per ATO), and the delivery of agreed feedstock volumes at a Beneficiation Fee of $100/tonne in Year 1, escalating 2.5%/year. Zero capex. Zero construction debt. Zero operating liability. The region's ATO operators retain collection and transport responsibilities.
  • Cosa si impegna la regione: Un Accordo di Fornitura Circolare di 30 anni che autorizza il dispiegamento Build-Own-Operate di Carbotura su tre siti industriali (uno per ATO), e la consegna dei volumi di feedstock concordati a una Tariffa TMC di $100/tonnellata nell'Anno 1, con escalation del 2,5%/anno. Zero capex. Zero debito costruttivo. Zero responsabilità operativa.
  • What the region receives: Year 1 — gross cost displacement of $42/tonne below current FWDC on every tonne processed (Beneficiation Fee paid, Circular Royalty™ not yet begun). From Month 13 — Circular Royalty™ receipts commencing at $120/tonne per tonne processed, escalating annually (separate transaction from Beneficiation Fee per the Separate Transaction Principle, MR §4.8). Steady state — per-tonne Royalty − Fee margin growing from +$17.50/tonne at Month 13 to +$93.46/tonne by Year 30. At 3,000 TPD full deployment, the region receives ~$311M in annual Circular Royalty™ receipts by Year 30 against a Beneficiation Fee of ~$191M paid — a per-tonne Royalty − Fee spread of ~$120M/yr.
  • Cosa riceve la regione: Anno 1 — spostamento del costo lordo di $42/tonnellata al di sotto del FWDC attuale per ogni tonnellata lavorata. Dal Mese 13 — pagamenti del Canone Circolare a partire da $120/tonnellata. Regime stazionario — vantaggio fiscale netto crescente da +$17,50/tonnellata al Mese 13 a +$93,46/tonnellata all'Anno 30. Con 3.000 TPD pieni, la regione riceve ~$311M in Canone Circolare annuo all'Anno 30.
  • Decision window: The WTE Livorno facility closes end 2027, removing ~68,000 TPY of processing capacity from ATO Toscana Costa. Phase Initial COD at Q4 2028 can directly absorb this gap — but authorization, site confirmation, and CSA execution must occur no later than Q2 2027 to protect this window. The latest date to authorize the Joint Working Group phase and protect Phase Initial COD is Q1 2027.
  • Finestra decisionale: L'impianto WTE di Livorno chiude a fine 2027, rimuovendo ~68.000 TPY di capacità dall'ATO Toscana Costa. Il COD della Fase Iniziale al Q4 2028 può assorbire direttamente questo divario — ma autorizzazione, conferma del sito ed esecuzione del CSA devono avvenire entro Q2 2027. La data più tarda per autorizzare lo Studio di Fattibilità è Q1 2027.

§1 — Commercial Structure and Decision Window §1 — Struttura Commerciale e Finestra Decisionale

Regulatory Predicate Transition (RPT) Transizione del Predicato Normativo (RPT) — percorso di uscita dal dominio dei rifiuti

Advanced Circular Manufacturing is a manufacturing process, not a waste-management activity. Microwave Catalytic Reforming operates in an anoxic, oxygen-free, sub-atmospheric environment — mechanistically incompatible with combustion or biological degradation. ACM does not fit within the waste domain and does not operate under waste-domain statutes. The Regulatory Predicate Transition (RPT) — also framed as the dewaste pathway — is the coordinated regulatory shift from legacy disposal-predicate statutes onto manufacturing-predicate classifications. 100% elemental recycling of the municipal material stream requires this transition. Manufacturing NAICS 325180 · 325998 · 327992 · 331110 · 331314 · 331492 (6-code ACM set) plus EPA RCRA §1004(27) / 40 CFR §261.2(e) exclusion pathway in the US; ISIC Rev.4 20-25 + UN CPC 89 internationally. In many jurisdictions the required authorities already exist in latent form within existing statutes; in others the transition requires primary-authority amendments. The Joint Working Group phase includes a regulatory engagement workstream to shepherd the RPT alongside site permitting. Both parties commit to the RPT pathway. Carbotura brings the process-classification evidence, regulatory engagement expertise from prior ACM deployments, and the legal-technical framework. The counterparty brings the standing to engage the local regulator, the political mandate for the transition, and — where applicable — legacy statutory authorities that can be re-instrumented for manufacturing use. The endpoint is categorical: manufacturing classification across all permitting, licensing, and regulatory contexts. Interim bridging authorities may apply during the transition.

L'impegno di entrambe le parti in questo engagement è di percorrere insieme la Transizione del Predicato Normativo (RPT) — anche detta la via di uscita dal dominio dei rifiuti — verso una classificazione al fatto che l'impianto di Produzione Circolare Avanzata riceva e mantenga la classificazione di impianto manifatturiero — ATECO 2007 20.13, 20.59, 23.99, 24.10, 24.42 o 24.45 — per tutte le finalità di autorizzazione, licenza e regolamentazione ai sensi del D.Lgs. 152/2006 (Testo Unico Ambientale) e della Direttiva Quadro Rifiuti UE 2008/98/CE. Il Microwave Catalytic Reforming opera in un ambiente anossico, privo di ossigeno e sub-atmosferico; è meccanisticamente incompatibile con la combustione e non è un processo di trattamento dei rifiuti solidi. Qualora un'autorità (ARPAT, Regione Toscana, gestore ATO o autorità competente UE) applicasse la classificazione trattamento rifiuti ATECO 38.21, 38.22 o 38.30 all'impianto ACM o ai suoi flussi di feedstock, Carbotura si ritirerà dall'engagement senza penali. Nessun impegno di capitale e nessun COD procederà in caso di errata classificazione.

Regulatory basis: EU Waste Framework Directive 2008/98/EC Art. 6 (end-of-waste) · D.Lgs. 152/2006 (Testo Unico Ambientale) Part IV · ATECO 2007 / NACE Rev. 2 manufacturing codes 20.13, 20.59, 23.99, 24.10, 24.42, 24.45 · ARPAT (Agenzia Regionale per la Protezione Ambientale della Toscana) permitting jurisdiction Base normativa: Direttiva Quadro Rifiuti UE 2008/98/CE Art. 6 (fine del regime di rifiuti) · D.Lgs. 152/2006 (Testo Unico Ambientale) Parte IV · Codici manifatturieri ATECO 2007 / NACE Rev. 2: 20.13, 20.59, 23.99, 24.10, 24.42, 24.45 · Competenza autorizzativa ARPAT (Agenzia Regionale per la Protezione Ambientale della Toscana)

§1.1 — The Circular Supply Agreement (CSA)§1.1 — L'Accordo di Fornitura Circolare (CSA)
ParameterParametro Carbotura CommitsCarbotura si Impegna Region / ATO CommitsRegione / ATO si Impegna
StructureStrutturaBuild-Own-Operate (BOO) · 30-year term
CapitalCapitale 100% Carbotura-financed — $397.5M Phase Initial; $1,777.5M full deploymentFinanziamento 100% Carbotura — $397,5M Fase Iniziale; $1.777,5M dispiegamento completo Zero capex. Zero construction debt. Zero operating liability.Zero capex. Zero debito costruttivo. Zero responsabilità operativa.
Facility ownershipProprietà impianti Carbotura owns and operates all three ACM facilities for the full 30-year termCarbotura possiede e gestisce tutti e tre gli impianti ACM per i 30 anni del contratto Region / ATOs provide site access and feedstock deliveryRegione / ATO fornisce accesso al sito e consegna del feedstock
Beneficiation Fee obligationObbligo Tariffa TMC Processes all delivered feedstock per CSA specificationsTratta tutto il feedstock consegnato secondo le specifiche del CSA Pays $100/tonne Year 1 Beneficiation Fee per tonne delivered, escalating 2.5%/yearPaga $100/tonnellata Tariffa TMC Anno 1 per tonnellata consegnata, con escalation 2,5%/anno
Circular Royalty™Canone Circolare Pays Circular Royalty™ commencing Month 13 per contractual formula at multiplier 120% in Year 1, rising 1pp per year, applied to that year’s Beneficiation Fee, escalating +1pp/yearPaga Canone Circolare a partire dal Mese 13 per formula contrattuale al tasso base del 120% × Tariffa TMC Anno 1, con escalation +1pp/anno
Circular MaterialsCircular Materials Retains full title to all manufactured outputs; provides carbon accounting and annual reportingMantiene la piena proprietà di tutti gli output manifatturieri; fornisce contabilità del carbonio e reportistica annuale
Performance guaranteeGaranzia di performance Designed for near-zero landfill disposition; near-zero residual; designed availability ≥95%Progettato per smaltimento in discarica quasi zero; residuo quasi zero; disponibilità progettata ≥95% Minimum volume commitments per agreed scheduleImpegni di volume minimo per il calendario concordato
Decision Window — Hard DateFinestra Decisionale — Data Inderogabile

The WTE Livorno closure (est. end 2027) removes ~68,000 TPY from ATO Toscana Costa with no replacement infrastructure contracted. Phase Initial COD at Q4 2028 can absorb this gap — but achieving Q4 2028 COD requires construction start no later than Q4 2026, which requires Carbotura authorization and CSA execution no later than Q2 2027. The Joint Working Group phase (3 months) must commence no later than Q1 2027. That window opens when the Region and ATOs authorize it. Not when they think about it.

La chiusura del WTE di Livorno (stim. fine 2027) rimuove ~68.000 TPY dall'ATO Toscana Costa. Il COD della Fase Iniziale al Q4 2028 richiede l'avvio della costruzione entro Q4 2026, che richiede l'autorizzazione Carbotura e l'esecuzione del CSA entro Q2 2027. Lo Studio di Fattibilità (3 mesi) deve iniziare entro Q1 2027.

§1.5 — CSA Structure §1.5 — Quadro Elettorale CSA

At CSA execution, Regione Toscana The Exogenesis™ Royalty Bonus is a universal additive stream available as a CSA add-on, activated when Peccioli landfill (Pisa) is deeded at signing. T0: Q2 2027 (EU pipeline canonical default).

All'esecuzione del CSA, Regione Toscana elegge tra (Elezione Standard con Tariffa TMC + Canone Circolare) e (Scambio Canone Regionale con €0 tariffa + Corrispettivo Scambio Attivo). Il Bonus Canone Exogenesis™ è disponibile con entrambe le elezioni. T0: Q2 2027.

Italy / Tuscany Application Note: Both options are commercially available to Regione Toscana as an Italian constitutional sub-national authority with legislative competence under Title V. is legitimately applicable per the Region’s constitutional capacity — Italian atto pubblico via Agenzia delle Entrate provides the enabling fiscal instrument. ZES (Zona Economica Speciale) designation provides the tax abatement framework.

Nota applicativa Italia / Toscana: La CSA si applica come struttura unica per Regione Toscana, autorità sub-nazionale costituzionale italiana con competenza legislativa ai sensi del Titolo V. presso Agenzia delle Entrate. La designazione ZES fornisce il quadro delle agevolazioni fiscali.

Exogenesis™ Royalty Opportunity — Peccioli Landfill, PisaOpportunità Canone Exogenesis™ — Discarica Peccioli, Pisa

Peccioli (Pisa) is the largest active landfill in Tuscany and the primary qualifying asset for the Exogenesis™ Royalty Bonus. At CSA execution, all post-closure care, leachate management, and IPSAS 19 environmental obligations transfer to Carbotura — extinguishing Regione Toscana’s balance sheet provision. Carbotura deploys the Exogenesis™ Programme (APS mechanical sorting + fully electric extraction fleet) within 3–7 years post-COD. Additional Tuscany regional landfills from the network of nine active sites may be added via Programme amendments as their closure timelines are confirmed with the three ATO operators (Alia SpA · Retiambiente SpA · ATO Sud).

Peccioli (Pisa) è la discarica attiva più grande della Toscana e il principale attivo qualificante per il Bonus Canone Exogenesis™. All’esecuzione del CSA, tutti gli obblighi IPSAS 19 trasferiscono a Carbotura, estinguendo la passività patrimoniale di Regione Toscana. Ulteriori discariche regionali della rete di nove siti attivi possono essere aggiunte tramite emendamenti al Programma con i tre gestori ATO (Alia SpA · Retiambiente SpA · ATO Sud).

§2 — Deployment Architecture §2 — Architettura di Dispiegamento

§2.1 — Phase Configuration§2.1 — Configurazione per Fase
PhaseFase TPD Modules (3 sites)Moduli (3 siti) Annual FeedstockFeedstock Annuale % Addressable% Indirizzabile COD Carbotura CapExCapEx Carbotura
Phase InitialFase Iniziale 600 TPD 3 sites × 2 modules3 siti × 2 moduli 219,000 TPY 10.1% Q4 2028 $397.5M
Phase MediumFase Media 1,500 TPD 3 sites × 5 modules3 siti × 5 moduli 547,500 TPY 25.3% Q4 2029 $915M
Phase ExpandedFase Espansa 3,000 TPD 3 sites × 10 modules3 siti × 10 moduli 1,095,000 TPY 50.7% Q4 2031 $1,777.5M

CapEx: first 100 TPD module $75M; each additional 100 TPD $57.5M (Carbotura standard parameters). Region bears zero CapEx.

CapEx: primo modulo 100 TPD $75M; ogni 100 TPD aggiuntivo $57,5M (parametri standard Carbotura). La regione non sostiene alcun CapEx.

Phase Initial
Fase Iniziale
600 TPD
Q4 2028
Phase Medium
Fase Media
1,500 TPD
Q4 2029
Phase Expanded
Fase Espansa
3,000 TPD
Q4 2031
Regional Total
Totale Regionale
5,917 TPD total regional stream
100% stream
100% flusso
§2.2 — BOO Capital Structure§2.2 — Struttura del Capitale BOO
Zero Public Authority Capital RequirementZero Requisito di Capitale per l'Autorità Pubblica
  • Carbotura finances all facility construction, commissioning, and lifecycle maintenance
  • No regional bond issuance, no EU grant dependency, no municipal budget allocation required
  • ATO operator obligations: feedstock delivery at agreed volumes; site access and utilities connection
  • Carbotura bears all technology performance risk — the Beneficiation Fee is fixed regardless of output volumes or Circular Materials market conditions
  • The region's maximum financial exposure is the Beneficiation Fee × delivered volume — equivalent to the existing disposal cost it currently pays anyway
  • Carbotura finanzia tutta la costruzione degli impianti, la messa in servizio e la manutenzione del ciclo di vita
  • Nessuna emissione di obbligazioni regionali, nessuna dipendenza da sovvenzioni UE, nessun bilancio municipale richiesto
  • Obblighi dell'operatore ATO: consegna del feedstock ai volumi concordati; accesso al sito e connessione delle utenze
  • Carbotura sostiene tutti i rischi di performance tecnologica — la Tariffa TMC è fissa indipendentemente dai volumi di output
  • La massima esposizione finanziaria della regione è la Tariffa TMC × volume consegnato — equivalente al costo di smaltimento esistente già pagato
§2.3 — Feedstock Stream Coverage by Phase§2.3 — Copertura dei Flussi Feedstock per Fase
StreamFlusso Phase InitialFase Iniziale Phase MediumFase Media Phase ExpandedFase Espansa Access StatusStatus Accesso
RDF/SRF export (~160,000 TPY)Export RDF/SRF (~160.000 TPY)✓✓✓IMMEDIATE
Industrial textiles — Prato (~75,000 TPY)Tessuti industriali — Prato (~75.000 TPY)✓✓✓IMMEDIATE
Post-separation residual (~689,000 TPY)Residuo post-separazione (~689.000 TPY)✓✓CONDITIONAL
Organic / biowaste (~423,000 TPY)Organico / biowaste (~423.000 TPY)✓CONDITIONAL
C&D fines, biosolids, otherFini C&D, fanghi, altro✓CONDITIONAL

§2.4 — Site Candidate Analysis §2.4 — Analisi dei Siti Candidati

Three Priority Zones identified — one per ATO. Selection criteria: proximity to primary feedstock sources, existing industrial zoning, infrastructure co-location, and ATO concession alignment. Click a zone card to focus the map.

Tre Zone Prioritarie identificate — una per ATO. Criteri di selezione: prossimità alle fonti di feedstock, zonizzazione industriale esistente, co-localizzazione infrastrutturale e allineamento con la concessione ATO. Clicca una scheda zona per focalizzare la mappa.

Source: Regione Toscana ATO zoning records; Italian industrial land registry; Carbotura site assessment criteria. Zones are candidate zones pending feasibility confirmation — not committed sites. Fonte: Catasto zonizzazione ATO; registro italiano terreni industriali; criteri di valutazione siti Carbotura. Le zone sono candidate in attesa di conferma di fattibilità — non siti impegnati.

Site Candidate Summary TableTabella Riepilogativa Siti Candidati
PriorityPriorità Zone / LocationZona / Luogo Est. AcreageSuperficie Stimata ZoningZonizzazione Land AuthorityAutorità Fondiaria Co-location AdvantageVantaggio Co-localizzazione Key ConsiderationConsiderazione Chiave
P1 Zona Industriale Prato Sud
(Prato / Campi Bisenzio)
Zona Industriale Prato Sud
(Prato / Campi Bisenzio)
~8–12 ha D1 Industrial / ArtisanalD1 Industriale / Artigianale Comune di Prato / Comune di Campi BisenzioComune di Prato / Comune di Campi Bisenzio 5–8 km from Prato textile generators; A11/A1 motorway junction; Alia transfer network; Florence Osmannoro logistics hub 12 km5–8 km dai generatori tessili di Prato; svincolo A11/A1; rete di trasferimento Alia; hub logistico Osmannoro 12 km Alia concession active to 2037; co-operation agreement required; ACM WTE distinction must be documented in planning submissionConcessione Alia attiva fino al 2037; accordo di cooperazione richiesto; distinzione ACM-WTE da documentare
P2 Porto Industriale di Livorno
(Livorno / Collesalvetti)
Porto Industriale di Livorno
(Livorno / Collesalvetti)
~10–15 ha D2 Industrial / Port ZoneD2 Industriale / Zona Porto Autorità di Sistema Portuale del Mar Tirreno SettentrionaleAutorità di Sistema Portuale del Mar Tirreno Settentrionale Adjacent to WTE Livorno closure site (~1.5 km); port infrastructure for Circular Materials export; Retiambiente transfer network; SGS logistics corridorAdiacente al sito di chiusura WTE Livorno (~1,5 km); infrastruttura portuale per export Circular Materials; rete di trasferimento Retiambiente Port Authority jurisdiction — separate permitting authority from Regione Toscana; ADSP approval required; logistics premium for Circular Materials export is an advantageGiurisdizione Autorità Portuale — autorità di permesso separata dalla Regione Toscana; approvazione ADSP richiesta
P3 Zona Industriale Arezzo Nord
(Arezzo / Capolona)
Zona Industriale Arezzo Nord
(Arezzo / Capolona)
~7–10 ha D1 IndustrialD1 Industriale Comune di Arezzo / Comune di CapolonaComune di Arezzo / Comune di Capolona 4 km from San Zeno RRF complex; A1 motorway access; SEI Toscana (Iren) transfer infrastructure; covers Siena + Grosseto catchment with <85 km average haul4 km dal polo San Zeno; accesso A1; infrastruttura SEI Toscana; copre bacino Siena + Grosseto con <85 km di percorso medio SEI Toscana concession renewal timing uncertain; Iren Group relationship management; longer haul from Grosseto (~90 km) is the key logistics constraintScadenza concessione SEI Toscana incerta; gestione relazione Iren Group; percorso più lungo da Grosseto (~90 km) è il vincolo logistico chiave
Co-location Proximity Analysis — Driving DistancesAnalisi di Prossimità Co-localizzazione — Distanze di Guida
From / ToDa / A P1 — Prato Sud (km)P1 — Prato Sud (km) P2 — Livorno Porto (km)P2 — Livorno Porto (km) P3 — Arezzo Nord (km)P3 — Arezzo Nord (km)
Prato textile districtDistretto tessile Prato~5–8 km~90 km~100 km
WTE Livorno (closing 2027)WTE Livorno (chiusura 2027)~95 km~1–2 km~120 km
Peccioli landfill (largest in Tuscany)Discarica Peccioli (la più grande)~65 km~35 km~85 km
San Zeno WTE / ArezzoWTE San Zeno / Arezzo~95 km~120 km~4 km
Poggibonsi WTE / SienaWTE Poggibonsi / Siena~60 km~80 km~55 km
Florence / Alia transfer hubFirenze / hub trasferimento Alia~18 km~95 km~80 km
Lucca / Massa-Carrara (Retiambiente)Lucca / Massa-Carrara (Retiambiente)~60 km~55 km~160 km
Grosseto (SEI Toscana)Grosseto (SEI Toscana)~175 km~130 km~90 km
Priority 1 Finding — Prato SudRisultato Priorità 1 — Prato Sud

Zona Industriale Prato Sud is the Priority 1 candidate on three co-location grounds: (1) it sits within 5–8 km of Europe's largest industrial textile recycling district — Prato's ~75,000 TPY overflow stream is the Phase Initial's highest-priority IMMEDIATE feedstock requiring no ATO contract renegotiation; (2) A11/A1 motorway junction enables efficient access to the entire ATO Toscana Centro catchment (Florence, Pistoia, Prato — ~2,250 TPD combined); and (3) it is within Alia Servizi Ambientali's service territory under a concession secured to 2037, providing the strongest contractual anchor for a long-term processing agreement across all three zones.

La Zona Industriale Prato Sud è il candidato Priorità 1 per tre ragioni di co-localizzazione: (1) si trova a 5–8 km dal più grande distretto industriale di riciclo tessile d'Europa — il flusso di eccedenze di ~75.000 TPY di Prato è il feedstock IMMEDIATO di più alta priorità; (2) lo svincolo A11/A1 consente un accesso efficiente a tutto il bacino ATO Toscana Centro; (3) si trova nel territorio di servizio di Alia Servizi Ambientali con concessione garantita fino al 2037.

§2.5 — Phase Initial Feedstock Sufficiency§2.5 — Sufficienza Feedstock Fase Iniziale
Phase Initial Is Fully Supportable Without ATO RenegotiationLa Fase Iniziale È Completamente Supportabile Senza Rinegoziazione ATO

Phase Initial requires 600 TPD (219,000 TPY) across three sites. The two IMMEDIATE streams — RDF/SRF export (~160,000 TPY / 438 TPD) and industrial textile overflow from Prato (~75,000 TPY / 207 TPD) — together provide ~235,000 TPY (~644 TPD) with no ATO contract amendment required. Phase Initial is oversubscribed on IMMEDIATE streams alone by 7%. The RDF/SRF export stream is the higher-value target: currently costing ~€140/tonne (including logistics) — $40/tonne more expensive than the ACM Beneficiation Fee — making the cost displacement argument immediate and unambiguous.

La Fase Iniziale richiede 600 TPD (219.000 TPY) su tre siti. I due flussi IMMEDIATI — export RDF/SRF (~160.000 TPY) e eccedenza tessile industriale di Prato (~75.000 TPY) — forniscono insieme ~235.000 TPY (~644 TPD) senza alcun emendamento del contratto ATO. La Fase Iniziale è sovra-iscritta solo dai flussi IMMEDIATI del 7%.

Map requires a Google Maps API key.
Set GOOGLE_MAPS_API_KEY in config.js.
All candidate zone data is visible in the panel →

La mappa richiede una chiave API Google Maps.
Impostare GOOGLE_MAPS_API_KEY in config.js.
Tutti i dati delle zone candidate sono visibili nel pannello →

ACM Site Candidate ZonesZone Siti Candidati ACM
P1 — EmeraldP1 — Verde
P2 — BlueP2 — Blu
P3 — MustardP3 — Senape
Feedstock refRif. feedstock

§3 — Economic Structure — Beneficiation Fee (TMC Fee) §3 — Struttura Economica — Tariffa TMC

§3.1 — FWDC Planning Basis§3.1 — Base di Pianificazione FWDC
ParameterParametro ValueValore Source TypeTipo Fonte
FWDC — Tuscany blendedFWDC — Toscana combinato$142/tonne (€130/tonne)MODELED
Beneficiation Fee Year 1Tariffa TMC Anno 1$100/tonneLOCKED
Year 1 gross cost displacementSpostamento costo lordo Anno 1$42/tonne (30% below FWDC)MODELED
Beneficiation Fee annual escalatorEscalation annuale Tariffa TMC2.5%/yearLOCKED
Beneficiation Fee at Year 10Tariffa TMC all'Anno 10$128.01/tonneLOCKED
Beneficiation Fee at Year 30Tariffa TMC all'Anno 30$203.28/tonneLOCKED
§3.2 — Beneficiation Fee Formula§3.2 — Formula Tariffa TMC
Beneficiation Fee Formula (Carbotura standard parameters)
TMC_Fee = MAX($100, MIN($150, FWDC − $5))
Floor: $100/tonne · Ceiling: $150/tonne · Applied to planning-basis FWDC of $142/tonne → Beneficiation Fee = $100/tonne (floor applies)
Assumption Disclosure — FWDC BasisDivulgazione Assunzione — Base FWDC

The FWDC of $142/tonne is a MODELED value derived from ISPRA regional service cost benchmarks for central Italy. No contracted ATO disposal rates have been provided. If the verified FWDC at feasibility study stage falls below $105/tonne, the Beneficiation Fee floor of $100/tonne still applies and the economics are unchanged from this Proposal. If FWDC exceeds $150/tonne (EU tax reform scenario), the $150 ceiling applies. EUR/USD rate of 1.09 applied — Carbotura will offer EUR-denominated pricing option at contract structuring.

Il FWDC di $142/tonnellata è un valore STIMATO derivato dai benchmark ISPRA. Se il FWDC verificato allo stadio dello studio di fattibilità scende sotto $105/tonnellata, si applica comunque il pavimento TMC di $100/tonnellata. Se supera $150/tonnellata, si applica il soffitto di $150. Tasso EUR/USD 1,09 applicato — Carbotura offrirà un'opzione di tariffazione in EUR alla strutturazione del contratto.

§3.3 — Annual Beneficiation Fee Obligation by Phase§3.3 — Obbligo Annuale Tariffa TMC per Fase
PhaseFase TPD Annual VolumeVolume Annuale Beneficiation Fee Year 1Tariffa TMC Anno 1 Annual Obligation Y1Obbligo Annuale A1 Beneficiation Fee Y10Tariffa TMC A10 Annual Obligation Y10Obbligo Annuale A10
Phase InitialFase Iniziale600219,000 TPY$100/t$21.9M$128.01/t$28.0M
Phase MediumFase Media1,500547,500 TPY$100/t$54.75M$128.01/t$70.1M
Phase ExpandedFase Espansa3,0001,095,000 TPY$100/t$109.5M$128.01/t$140.2M

§4 — Circular Royalty™ — Contractual Definition §4 — Canone Circolare — Definizione Contrattuale

§4.0 — Circular Royalty™ §4.0 — Canone Circolare™

Standard CSA: Regione Toscana pays a per-tonne Beneficiation Fee on feedstock delivered; Carbotura pays a Circular Royalty™ calibrated to 120% of the corresponding Beneficiation Fee, +1pp/yr escalator, beginning Month 13 on a rolling monthly basis. By design, the per-tonne Circular Royalty™ exceeds the per-tonne Beneficiation Fee from Year 2 onward (separate transactions, never netted). Currency: EUR primary.

Elezione standard del CSA: Regione Toscana paga una Tariffa TMC per tonnellata consegnata; Carbotura paga un Canone Circolare calibrato al 120% della Tariffa corrispondente, +1pp/anno, a partire dal Mese 13 su base mensile continua. Per design, il Canone per tonnellata supera la Tariffa per tonnellata dall’Anno 2 in poi (transazioni separate, mai compensate). Valuta: EUR primaria.

Three Required Canonical StatementsTre Dichiarazioni Canoniche Obbligatorie

1. The Circular Royalty™ is a contractual obligation of Carbotura — not a conditional rebate, a performance bonus, or a discretionary payment. It is locked in the CSA at signing and not subject to Carbotura's business performance or Circular Materials market conditions.

1. Il Canone Circolare è un obbligo contrattuale di Carbotura — non uno sconto condizionale, un bonus di performance o un pagamento discrezionale. È bloccato nel CSA alla firma e non è soggetto alle condizioni di business di Carbotura.

2. The Circular Royalty™ commences 13 months after the first corresponding Beneficiation Fee payment — not at COD, not at a fixed calendar date, but 13 months after each monthly Beneficiation Fee period. It operates on a rolling lagged cash flow basis.

2. Il Canone Circolare inizia 13 mesi dopo il primo corrispondente pagamento della Tariffa TMC — non al COD, ma 13 mesi dopo ogni periodo mensile della Tariffa TMC. Opera su base di flusso di cassa ritardato rotante.

3. The Circular Royalty™ is designed to exceed the Beneficiation Fee per tonne by Year 2 onward — meaning the per-tonne Royalty − Fee spread is designed to be positive from Month 13 (reported as separate transactions per the Separate Transaction Principle, MR §4.8), and growing every year thereafter by the annual escalation spread.

3. Il Canone Circolare è progettato per superare la Tariffa TMC per tonnellata dal Secondo Anno in poi — il che significa che la posizione fiscale regionale netta è progettata per essere positiva dal Mese 13 e in crescita ogni anno successivo.

Circular Royalty™ Formula (Contractual)
Royalty(m+13) = TMC(m) × Royalty_Rate(m)
Where: m = payment month · Royalty(m+13) = Circular Royalty™ paid at month m+13 · TMC(m) = Beneficiation Fee paid at month m · Royalty_Rate(m) = 120% + ((floor(m/12)) × 1%) per year
§4.0.1 — Royalty Parameter Table§4.0.1 — Tabella Parametri Canone Circolare
ParameterParametro ValueValore ClassificationClassificazione
Royalty base rateTasso base Canone120% of that year's Beneficiation Fee per tonneCARBOTURA STANDARD
Royalty base amountImporto base Canone$120/tonne (120% × $100)LOCKED
Beneficiation Fee escalatorEscalation Tariffa TMC2.5%/yearCARBOTURA STANDARD
Royalty rate escalatorEscalation tasso Canone+1 percentage point/yearCARBOTURA STANDARD
Payment lagRitardo pagamento13 months after corresponding Beneficiation FeeFIXED — NOT NEGOTIABLE
Payment basisBase pagamentoRolling monthlyCARBOTURA STANDARD
CSA termDurata CSA30 yearsCARBOTURA STANDARD
§4.0.2 — Three Fiscal Periods§4.0.2 — Tre Periodi Fiscali
Period 1 — Pre-Royalty
Periodo 1 — Pre-Canone
Month 1–12
Beneficiation Fee only: $100/tonne per month. Fee outflow: $100/tonne (vs. current FWDC of $142/tonne). Gross saving: $42/tonne from Day 1. Circular Royalty™ not yet begun.
Solo Tariffa TMC: $100/tonnellata al mese. Risparmio lordo: $42/tonnellata dal Giorno 1.
Period 2 — Royalty Ramp
Periodo 2 — Rampa Canone
Month 13+
Circular Royalty™ commences. Month 13: Royalty = $120/tonne; Beneficiation Fee = $102.50/tonne. Per-tonne Royalty − Fee margin: +$17.50/tonne (separate transactions).
Canone Circolare inizia. Mese 13: Canone = $120/tonn; Tariffa TMC = $102,50/tonn. Posizione netta: +$17,50/tonnellata.
Period 3 — Steady State
Periodo 3 — Regime Stazionario
Year 5+
Royalty escalation outpaces Beneficiation Fee escalation by design. Year 5: Royalty − Fee +$26.49/tonne. Year 10: Royalty − Fee +$30.84/tonne. Year 30: Royalty − Fee +$80.91/tonne (3,000 TPD = ~$88.6M annual Royalty − Fee margin).
L'escalation del canone supera l'escalation TMC per design. Anno 5: netto +$26,49/tonn. Anno 30: netto +$80,91/tonn.
§4.0.3 — Year-by-Year Cash Flow (per tonne processed; Phase Expanded)§4.0.3 — Flusso di Cassa Anno per Anno (per tonnellata; Fase Espansa)
YearAnno Avoided Disposal/tSmaltimento Evitato/t Beneficiation Fee/tonneTariffa TMC/tonn Royalty RateTasso Canone Royalty/tonneCanone/tonn
Y1 (pre-royalty)$142.00$100.00$0
Y2 (Month 13+)$145.55$102.50120%$120.00
Y5$154.78$110.38124%$136.87
Y10$170.40$128.01129%$165.13
Y20$206.57$166.23139%$231.06
Y30$250.07$203.28149%$302.89
Fiscal Position — Three Gross Items, Years 1–20 ($/tonne · Phase Expanded 3,000 TPD)
Posizione Fiscale — Tre Voci Lorde, Anni 1–20 ($/tonnellata · Fase Espansa 3.000 TPD)
Royalty income exceeds Beneficiation Fee from Year 2. Avoided disposal cost is present from Year 1. All figures are gross — not pre-netted. Year 1 Royalty bar shown as amber placeholder: royalty commences Month 13.
Il Canone supera la Tariffa TMC dall'Anno 2. Il costo di smaltimento evitato è presente dall'Anno 1. Tutte le cifre sono lorde — non pre-nettate. La barra Canone Anno 1 è un segnaposto: il Canone inizia al Mese 13.
Source: Carbotura Circular Advantage modeling · Registry values — FWDC $142/t, TMC $100/t, Royalty base 120%, +1pp/yr. All figures gross and independent. Fonte: Modellazione Carbotura Circular Advantage · Valori di Registro — FWDC $142/t, TMC $100/t, base Canone 120%, +1pp/anno. Tutte le cifre lorde e indipendenti.
§4.1 — Exogenesis™ Royalty Bonus (Peccioli Landfill, Pisa) §4.1 — Bonus Canone Exogenesis™ (Discarica Peccioli, Pisa)

Potential additive royalty stream, subject to Waste Characterization Study and mutual agreement — presented here as a structured option for discussion. If elected after study confirmation, activated when Regione Toscana (or Peccioli landfill operator on behalf of the Region) deeds Peccioli landfill to Carbotura at CSA execution (second atto pubblico, independent of Carbotura deploys the Exogenesis™ Programme — APS mechanical sorting + fully electric extraction fleet — within 3–7 years post-COD, alongside the primary Regenesis™ facility. Peccioli (Pisa) is the largest active landfill in Tuscany and the flagship Italian remediation case.

Flusso di canone additivo potenziale, soggetto a Studio di Caratterizzazione dei Rifiuti e accordo reciproco — presentato qui come opzione strutturale per la discussione. Se selezionato dopo la conferma dello studio, attivato quando Regione Toscana cede la discarica Peccioli a Carbotura all’esecuzione del CSA (secondo atto pubblico). Peccioli (Pisa) è la discarica attiva più grande della Toscana e il caso emblematico di bonifica italiano.

LandfillDiscarica StatusStato Extractable mass (estimate)Massa estraibile (stima) Exogenesis™ sequenceSequenza Exogenesis™
Peccioli (Pisa)Peccioli (Pisa) Active — largest in Tuscany · ~65km from ATO Centro boundaryAttiva — la più grande in Toscana · ~65km dal confine ATO Centro ~73,000 tpy extractable (planning basis)~73.000 tpy estraibili (base pianificazione) Year 5 post-COD — primaryAnno 5 post-COD — primario
Regional landfill network (8 additional sites)Rete discariche regionali (8 siti aggiuntivi) Active — closure timelines per ATO operators (Alia SpA · Retiambiente SpA · ATO Sud)Attive — scadenze chiusura per gestori ATO TBD per site — engineering studies requiredTBD per sito — studi tecnici richiesti Year 7+ post-COD — via Programme amendmentsAnno 7+ post-COD — tramite emendamenti al Programma
ParameterParametro ValueValore BasisBase
Royalty rateTasso canone€50.00/tonne extracted (Year 1 of extraction) (~$54.50 USD)€50,00/tonnellata estratta (Anno 1 di estrazione)CSA Schedule E.2
EscalationEscalation+1.0% per year from Year 2 of extraction+1,0% annuo dall’Anno 2 di estrazioneCSA Schedule E.2
Payment lagRitardo pagamento13 months after first extraction (rolling monthly)13 mesi dopo la prima estrazione (mensile continuo)CARBOTURA STANDARD
Programme onset (Peccioli)Inizio Programma (Peccioli)Year 5 post-COD (first extraction); Year 6 first royalty paymentAnno 5 post-COD (prima estrazione); Anno 6 primo pagamento canoneEngineering schedulePiano tecnico
Asset transfer (Peccioli)Trasferimento attivo (Peccioli)Italian atto pubblico registered with Agenzia delle Entrate at CSA execution (second instrument, independent of Regional landfill network added via Programme amendments.Atto pubblico italiano presso Agenzia delle Entrate all’esecuzione del CSA (secondo strumento). Rete discariche aggiunte tramite emendamenti.Italian civil lawDiritto civile italiano
Carbotura obligationsObblighi CarboturaAll post-closure care, leachate management, methane capture, groundwater monitoring, ARPAT compliance obligations transfer at CSA execution. Environmental Impairment Liability, Pollution Legal Liability, Post-Closure Performance Bond provided by Carbotura (replacing Region’s existing IPSAS 19 / IAS 37 provisions).Tutti gli obblighi di cura post-chiusura, gestione del percolato, monitoraggio ambientale trasferiti all’esecuzione del CSA, sostituendo le previsioni IPSAS 19 della Regione.CSA §6
StackingCumulazioneIndependent of and additive to the Circular Royalty™ OR8)Indipendente e additivo — mai compensato, transazioni separate (MR §4.8)Separate Transaction PrinciplePrincipio Transazione Separata
Exogenesis™ Royalty Cash Flow — Peccioli Anchor Case (EUR)Flusso Canone Exogenesis™ — Caso Ancoraggio Peccioli (EUR)
Year (post-COD)Anno (post-COD) Extraction tpy (Peccioli)Estrazione tpy (Peccioli) Rate €/tonneTasso €/tonn Annual Exogenesis™ Royalty EURCanone Exogenesis™ Annuo EUR ~USD (×1.09)~USD (×1,09)
Y1–4€0 (programme not yet operational)€0 (programma non ancora operativo)$0
Y5~73,000€50.00€0 (13-month lag — Year 6 first payment)€0 (ritardo 13 mesi)$0
Y6~73,000€50.00+€3,650,000~$3,978,500
Y10~73,000€52.02+€3,797,460~$4,139,231
Y20~73,000€57.47+€4,195,310~$4,572,888
Y30~73,000+€63.49+€4,634,770~$5,051,899
30-yr cumulative Exogenesis™ Royalty (Peccioli only)Cumulativo 30 anni Canone Exogenesis™ (solo Peccioli)~€103M~$112M

Peccioli anchor case: ~73,000 tpy planning basis (conservative). All ESTIMATED. Additional Tuscany regional landfills add to cumulative via Programme amendments. Exogenesis™ Royalty = €50 × 1.01n−2/tonne where n = years post-extraction start. USD at EUR/USD 1.09.Caso ancoraggio Peccioli: ~73.000 tpy base pianificazione (conservativo). Valori STIMATI. USD a EUR/USD 1,09.

IPSAS Balance-Sheet Event — Peccioli Post-Closure Liability ExtinguishmentEvento Patrimoniale IPSAS — Estinzione Passività Post-Chiusura Peccioli

At CSA execution, all post-closure care, leachate, methane, and ARPAT compliance obligations for Peccioli transfer to Carbotura — extinguishing Regione Toscana’s existing IPSAS 19 / IAS 37 post-closure care provision. Combined with Environmental Impairment Liability and Pollution Legal Liability assumption by Carbotura, this represents a material IPSAS balance-sheet event for Regione Toscana, independent of the Exogenesis™ Royalty cash flow. The network of nine regional landfills provides a long-dated extinguishment pipeline as additional Programme amendments are executed with ATO operators.

All’esecuzione del CSA, tutti gli obblighi post-chiusura, percolato, metano e conformità ARPAT per Peccioli trasferiscono a Carbotura, estinguendo la previsione IPSAS 19 di Regione Toscana. La rete dei nove siti regionali fornisce una pipeline di estinzione a lungo termine tramite emendamenti aggiuntivi con i gestori ATO.

§5 — Risk Register §5 — Registro dei Rischi

RiskRischio Key DriverFattore Chiave Who Bears ItChi Lo Sostiene MitigationMitigazione Residual ExposureEsposizione Residua
FWDC verification varianceVarianza verifica FWDC MODELED basis; no contracted rate providedBase stimata; nessuna tariffa contrattuale fornita Shared (Region confirms; Carbotura prices)Condiviso Joint Working Group phase confirms rate; TMC floor of $100/tonne protects economics regardlessStudio di Fattibilità conferma; pavimento TMC $100/tonn protegge l'economia Low — floor/ceiling structure absorbs varianceBasso — struttura pavimento/soffitto assorbe la varianza
Technology performancePerformance tecnologica ACM at commercial scale in Tuscany conditionsACM in scala commerciale CarboturaCarbotura Performance guarantee in CSA; designed availability ≥95%; residual stream management per contractGaranzia di performance nel CSA; disponibilità progettata ≥95% Low — Region bears zero technology riskBasso — la regione non sostiene rischi tecnologici
Timeline slippage — Phase Initial CODSlittamento — COD Fase Iniziale Authorization delays, site confirmation, Italian planning timelineRitardi autorizzativi, conferma sito, pianificazione italiana SharedCondiviso Early authorization of Joint Working Group phase (Q1 2027); parallel site permitting; ACM vs WTE distinction pre-filedAutorizzazione anticipata Studio di Fattibilità (Q1 2027); permitting parallelo; distinzione ACM-WTE pre-registrata Moderate — Italian permitting adds 3–6 months vs. standard; mitigated by early engagementModerato — autorizzazione italiana aggiunge 3–6 mesi
ATO concession constraintVincolo concessione ATO Three concurrent ATO concessions to 2033–2037; ARERA MTR-2 cost allocation rulesTre concessioni ATO concorrenti fino al 2033–2037; regole MTR-2 ARERA Region / ATO operatorsRegione / Operatori ATO Structure ACM as supplemental processing arrangement within concession; legal counsel on ARERA eligibility of Beneficiation Fee as disposal costStrutturare ACM come servizio supplementare nella concessione; consulenza legale su eleggibilità Tariffa TMC ARERA Moderate-High — Phase Initial uses only IMMEDIATE streams (no ATO renegotiation); Phase Medium requires co-operation agreementModerato-Alto — Fase Iniziale usa solo flussi IMMEDIATI; Fase Media richiede accordo di cooperazione
Competitive procurement / RFP conflictGara competitiva / conflitto RFP ATO operators may initiate alternative processing tendersGli operatori ATO potrebbero avviare gare per lavorazione alternativa RegionRegione Carbotura engagement through direct Regional authority; CSA execution before any ATO tender window; Phase Initial does not require ATO tender (IMMEDIATE streams)Coinvolgimento Carbotura attraverso autorità regionale; esecuzione CSA prima di qualsiasi finestra di gara ATO Moderate — resolved by executing CSA before tender is issued for post-2027 capacityModerato — risolto eseguendo il CSA prima dell'emissione della gara
Residual stream managementGestione flusso residuo Near-zero ACM design; Carbotura manages all outputsDesign quasi zero ACM; Carbotura gestisce tutti gli output CarboturaCarbotura CSA specifies residual management obligations; Region bears zero residual disposal cost for processed streamsIl CSA specifica gli obblighi di gestione del residuo; la regione non sostiene costi di smaltimento per i flussi lavorati LowBasso
PFAS regulatory evolutionEvoluzione normativa PFAS EU PFAS restrictions tightening (EU 2025 strategy); Tuscany textile waste may have elevated PFAS contentRestrizioni PFAS UE in aumento; i rifiuti tessili toscani potrebbero avere contenuto PFAS elevato SharedCondiviso ACM designed for PFAS destruction via anoxic elemental dissociation; Joint Working Group phase includes PFAS stream characterizationACM progettato per la distruzione PFAS tramite disgregazione molecolare anossica Low-Moderate — ACM provides a regulatory advantage vs. landfill (PFAS leachate) and WTE (PFAS in flue gas)Basso-Moderato — ACM fornisce un vantaggio normativo rispetto a discarica e WTE
EUR/USD currency riskRischio valutario EUR/USD Contracts USD-denominated; EUR/USD at 1.09 March 2026Contratti denominati in USD; EUR/USD a 1,09 marzo 2026 SharedCondiviso Carbotura to offer EUR-denominated pricing option at contract structuring; both parties can hedgeCarbotura offrirà opzione di tariffazione in EUR alla strutturazione del contratto Low — EUR option eliminates currency risk at sourceBasso — opzione EUR elimina il rischio valutario

§6 — Deployment Timeline §6 — Cronoprogramma di Dispiegamento

MilestoneMilestone DateData OwnerResponsabile NoteNota
Authorize Joint Working Group phaseAutorizzazione Studio di Fattibilità Comunitaria Q1 2027 ← LATEST Region / ATOsRegione / ATO Latest date to protect Q4 2028 Phase Initial CODData più tarda per proteggere il COD Q4 2028
Joint Working Group phase completeStudio di Fattibilità completatoQ2 2027CarboturaT0 + 3 monthsT0 + 3 mesi
CSA execution — all three sitesEsecuzione CSA — tutti e tre i sitiQ2 2027Both partiesEntrambe le parti
Site permitting — Phase InitialPermesso sito — Fase InizialeQ2–Q4 2027Carbotura + RegionCarbotura + RegioneACM vs. WTE distinction pre-filed at T0+2Distinzione ACM-WTE pre-registrata a T0+2
Phase Initial construction start (3 sites)Avvio costruzione Fase Iniziale (3 siti)Q4 2026CarboturaT0
WTE LIVORNO CLOSURE (est.)CHIUSURA WTE LIVORNO (stim.) END 2027 Retiambiente ~68,000 TPY capacity removed from ATO Costa — no contracted replacement~68.000 TPY capacità rimossa dall'ATO Costa — nessuna sostituzione contrattualizzata
Phase Initial COD — 3 × 200 TPD = 600 TPDCOD Fase Iniziale — 3 × 200 TPD = 600 TPD Q4 2028 Carbotura T0 + 24 months; first Beneficiation Fee payments commenceT0 + 24 mesi; iniziano i primi pagamenti Tariffa TMC
First Circular Royalty™ paymentPrimo pagamento Canone Circolare Q1 2030 Carbotura 13 months after Phase Initial COD; $120/tonne × processed volume; per-tonne Royalty exceeds per-tonne Fee (separate transactions)13 mesi dopo COD Fase Iniziale; $120/tonn × volume lavorato; Royalty per tonnellata supera Tariffa per tonnellata (transazioni separate)
Phase Medium full ops — 3 × 500 TPD = 1,500 TPDOperatività Fase Media — 3 × 500 TPD = 1.500 TPDQ4 2029CarboturaT0 + 36 months
EU Landfill Directive hard cap ≤10% (critical compliance)Limite UE Discariche ≤10% (conformità critica)2035Region / ItalyRegione / ItaliaACM Phase Expanded provides >50% of required diversionACM Fase Espansa fornisce >50% della deviazione richiesta
Phase Expanded full ops — 3 × 1,000 TPD = 3,000 TPDOperatività Fase Espansa — 3 × 1.000 TPD = 3.000 TPDQ4 2031CarboturaT0 + 60 months

§7 — Community Value Stack §7 — Valore per la Comunità

§7.1 — Direct Regional Fiscal Effects§7.1 — Effetti Fiscali Regionali Diretti
Fiscal ItemVoce Fiscale Phase Initial (Y2+)Fase Iniziale (A2+) Phase Expanded (Y2+)Fase Espansa (A2+) Year 30Anno 30
Gross cost displacement (Beneficiation Fee vs. FWDC)Spostamento costo lordo (Tariffa TMC vs. FWDC)+$9.2M/yr+$46.0M/yrGrowing with FWDC escalationCrescente con escalation FWDC
Circular Royalty™ receiptsEntrate Canone Circolare+$26.3M/yr+$131.4M/yr+$331.7M/yr
Royalty − Fee margin per tonne (separate transactions)Margine Royalty − Tariffa per tonnellata (transazioni separate)+$4.8M/yr+$19.2M/yr+$109.1M/yr
Landfill cost eliminated (844,000 TPY avoided at full deployment)Costo discarica eliminato (844.000 TPY evitate a pieno dispiegamento)~€51M/yrRegulatory compliance benefitBeneficio conformità normativa
TARI reduction potential per householdPotenziale riduzione TARI per famigliaJoint Working Group phase quantifiesQuantificato dallo Studio di FattibilitàJoint Working Group phase quantifiesQuantificato dallo Studio di Fattibilità
§7.2 — Regional Economic Effects (not to be mixed with fiscal receipts)§7.2 — Effetti Economici Regionali (da non mescolare con le entrate fiscali)
Economic ItemVoce Economica Phase InitialFase Iniziale Phase ExpandedFase Espansa
Direct FTE employment (3 sites)Occupazione diretta FTE (3 siti)~60 FTE~150 FTE
Indirect / supply-chain employmentOccupazione indiretta / filiera~150 jobs~375 jobs
Annual regional economic impactImpatto economico regionale annuale~$25M/yr~$65M/yr
Carbon avoided (vs. current system)Carbonio evitato (vs. sistema attuale)~130,000 TPY CO₂eq~730,000 TPY CO₂eq
30-year cumulative Circular Royalty™ receipts (3,000 TPD, gross)Royalty Circolare cumulativo 30 anni (3.000 TPD, lordo)~$1.45B Circular Royalty™ receipts (gross)

§8 — Why This Works in Tuscany §8 — Perché Funziona in Toscana

# Alignment FactorFattore di Allineamento EvidenceEvidenza
1Volume alignmentAllineamento volume 5,917 TPD total regional stream; Phase Expanded targets 50.7% (3,000 TPD). Phase Initial is only 10.1% of total — well within ATO supplemental service proportionality thresholds.5.917 TPD flusso regionale totale; Fase Espansa mira al 50,7% (3.000 TPD). Fase Iniziale solo 10,1% del totale.
2Infrastructure alignmentAllineamento infrastrutturale P1 at Prato Sud: 5–8 km from Europe's largest industrial textile recycling district (75,000 TPY immediate stream); direct A11/A1 access to Alia's entire transfer network. P2 at Livorno Porto: 1–2 km from closing WTE site — absorbs its capacity gap at Q4 2028 COD. P3 at Arezzo Nord: 4 km from San Zeno complex.P1 a Prato Sud: 5–8 km dal più grande distretto tessile industriale d'Europa. P2 a Livorno Porto: 1–2 km dal sito WTE in chiusura. P3 ad Arezzo Nord: 4 km dal complesso San Zeno.
3Contract timing alignmentAllineamento temporale contrattuale WTE Livorno closes end 2027. Phase Initial COD at Q4 2028 absorbs this gap with a 1-year margin. EU 2035 landfill cap requires 550,000 TPY diversion — Phase Expanded at Q4 2031 delivers this 4 years early.La chiusura WTE Livorno fine 2027 crea un divario che il COD Q4 2028 assorbe con un margine di 1 anno. Il limite UE 2035 richiede 550.000 TPY di deviazione — la Fase Espansa al Q4 2031 la consegna 4 anni prima.
4Policy alignmentAllineamento politico The January 2025 Regional Waste Plan explicitly prohibits new WTE but supports innovative non-incineration processing. ACM's anoxic elemental dissociation pathway falls squarely within the Plan's "filiera innovativa di trattamento" intent. Carbotura is the only BOO operator globally deploying at this technology-policy intersection.Il Piano Regionale 2025 vieta esplicitamente nuovi WTE ma supporta lavorazione non-incenerimento innovativa. La disgregazione molecolare anossica di ACM rientra nell'intento del Piano.
5EU regulatory driverDriver normativo UE Tuscany is Italy's single largest landfill user (844,000 TPY). The EU 2035 ≤10% landfill mandate requires diversion of ~550,000 additional TPY against zero approved alternative infrastructure. ACM Phase Expanded at 3,000 TPD closes this gap by itself — and generates Circular Royalty™ while doing so.La Toscana è il più grande utente italiano di discariche (844.000 TPY). Il mandato UE ≤10% richiede la deviazione di ~550.000 TPY aggiuntivi. ACM Fase Espansa a 3.000 TPD colma questo divario da sola.
6Economics specificitySpecificità economica The $142/tonne blended FWDC is derived from Tuscany-specific ISPRA regional cost benchmarks. The Beneficiation Fee of $100/tonne produces a $42/tonne gross saving on every tonne from Day 1 — using this community's own cost data, not generic benchmarks. The RDF/SRF export stream at ~€140/tonne is $40/tonne more expensive than the Beneficiation Fee — making the Phase Initial cost argument the most financially direct of any Carbotura deployment to date.Il FWDC combinato di $142/tonn è derivato dai benchmark ISPRA specifici per la Toscana. La Tariffa TMC di $100/tonn produce un risparmio lordo di $42/tonn su ogni tonnellata dal Giorno 1. Il flusso export RDF/SRF a ~€140/tonn è $40/tonn più costoso della Tariffa TMC.

Appendix A — Data Basis Appendice A — Base Dati

1. ISPRA — Rapporto Rifiuti Urbani 2025 (data year 2024). FWDC model basis. December 2025.

2. Carbotura standard parameters — Beneficiation Fee floor/ceiling structure, Royalty formula, CapEx schedule, employment multipliers. March 2026.

3. Retiambiente SpA — Relazione Tecnica Annuale 2024. ATO Toscana Costa concession data. June 2025.

4. Regione Toscana — Piano Regionale di Gestione dei Rifiuti (January 2025). WTE Livorno closure, innovation pathway confirmation.

5. ATO Toscana Centro — Aggiornamento Tariffario Biennale 2024–2025 — ALIA Servizi Ambientali. Concession term and service cost data. 2024.

6. European Environment Agency — EU Landfill Directive early warning assessment for Italy. 2022.

7. Cittadinanzattiva — Osservatorio Prezzi TARI 2024. Household waste cost data.

8. T24 Economia — "Dopo 3 anni il piano rifiuti della Toscana è legge." January 2025. RDF/SRF export volume confirmation.

9. Greenreport.it — AISA Impianti / San Zeno WTE expansion data. August 2024.

10. EIB — Acque SpA Basso Valdarno €130M financing. June 2023. WWTP operator verification.

Appendix B — Selective Glossary Appendice B — Glossario Selettivo

Beneficiation Fee (Manufacturing Service Fee / Tariffa del Servizio Manifatturiero)
The contractual per-tonne fee paid by a feedstock supplier to Carbotura for Total Material Conversion processing. Replaces the legacy disposal gate fee. In Tuscany: $100/tonne Year 1, escalating 2.5%/year, subject to MAX/MIN floor-ceiling formula vs. FWDC.
La tariffa contrattuale per tonnellata pagata da un fornitore di feedstock a Carbotura per la lavorazione TMC. In Toscana: $100/tonn Anno 1, con escalation 2,5%/anno.
Circular Royalty™ (Conversion Royalty / Canone Circolare)
A contractual cash payment by Carbotura to the feedstock supplier, commencing 13 months after the first Beneficiation Fee. Not a rebate. In Tuscany: base $120/tonne (120% × $100), escalating +1pp/year, on a rolling monthly lag basis.
Un pagamento contrattuale in contanti da Carbotura al fornitore di feedstock, iniziando 13 mesi dopo la prima Tariffa TMC. In Toscana: base $120/tonn, escalation +1pp/anno.
CSA — Circular Supply Agreement (Accordo di Fornitura Circolare)
The 30-year master contract governing feedstock supply, Beneficiation Fee, Circular Royalty™, performance obligations, and site access between the Region/ATOs and Carbotura.
Il contratto principale di 30 anni che disciplina la fornitura di feedstock, la Tariffa TMC, il Canone Circolare e gli obblighi di performance.
FWDC — Full Weighted Disposal Cost (Costo di Smaltimento Ponderato Totale)
Total per-tonne cost of the current feedstock disposal system inclusive of all gate fees, transport, levies, and capital recovery. Planning basis: $142/tonne (MODELED). Confirmed at Joint Working Group phase.
Costo totale per tonnellata del sistema di smaltimento attuale. Base di pianificazione: $142/tonn (STIMATO). Confermato allo Studio di Fattibilità.
Gross Cost Displacement (Spostamento Costo Lordo)
FWDC minus Beneficiation Fee = the per-tonne cost saving on every tonne processed from Year 1, before the Circular Royalty™ commences. In Tuscany Year 1: $142 − $100 = $42/tonne gross displacement.
FWDC meno Tariffa TMC = il risparmio per tonnellata su ogni tonnellata lavorata dall'Anno 1. In Toscana Anno 1: $142 − $100 = $42/tonn.
Per-Tonne Fiscal Flows (Flussi Fiscali per Tonnellata)
The two independent fiscal flows of the CSA, reported as separate transactions per the Separate Transaction Principle (MR §4.8) and never netted: (1) Beneficiation Fee paid by the Region to Carbotura per tonne of feedstock delivered; (2) Circular Royalty™ received by the Region from Carbotura, beginning 13 months after first Beneficiation Fee payment. In Tuscany at Month 13: per-tonne Royalty − Fee margin = +$17.50/tonne; at Year 30: +$99.61/tonne. The two flows are presented separately in all fiscal tables and never combined.
I due flussi fiscali indipendenti del CSA, riportati come transazioni separate secondo il Principio delle Transazioni Separate (MR §4.8) e mai compensati: (1) Tariffa di Beneficiamento pagata dalla Regione a Carbotura per tonnellata di alimentazione consegnata; (2) Canone Circolare ricevuto dalla Regione da Carbotura, a partire da 13 mesi dopo il primo pagamento della Tariffa. In Toscana al Mese 13: margine Royalty − Tariffa = +$17,50/tonn; all'Anno 30: +$99,61/tonn. I due flussi sono presentati separatamente in tutte le tabelle fiscali e mai combinati.
Pre-Royalty Period (Periodo Pre-Canone)
Months 1–12 after Phase Initial COD, during which the Beneficiation Fee is paid but no Circular Royalty™ has yet been earned. In Tuscany: Q4 2028 – Q4 2029 (months 1–12 post-COD). Note: gross cost displacement is still +$42/tonne during this period.
Mesi 1–12 dopo il COD della Fase Iniziale, durante i quali viene pagata la Tariffa TMC ma non è ancora stato maturato alcun Canone Circolare. In Toscana: Q4 2028 – Q4 2029.
BOO — Build-Own-Operate
Carbotura's project delivery model. Carbotura finances, constructs, owns, and operates the ACM facilities for the full CSA term. At no point does the Region/ATO hold ownership, construction debt, or operating liability.
Il modello di consegna del progetto Carbotura. Carbotura finanzia, costruisce, possiede e gestisce gli impianti ACM per tutta la durata del CSA. In nessun momento la Regione/ATO detiene proprietà, debito costruttivo o responsabilità operativa.
Was this Proposal useful? Questa Proposta è stata utile?